Law No 10/1998
regarding
Industrial Estates and Industrial Free Zones

CHAPTER SEVEN

Procedures Inside The Industrial free zone

Article (30)

It is not permissible for any physical or legal person to perform any industrial activity inside the industrial free zone, except with the industrial free zone certificate, which authorizes it to work in a single industrial free zone.

Article (31)

Applications to obtain industrial free zone certificate shall be submitted by project owners to the Director General of PIEFZA, who presents them to the Board of Directors no later than a month from the date of submission.  The Board of Directors shall respond within two weeks from the date of presentation.  Every decision to deny the application must be reasoned.

Article (32)

An application rejected pursuant to Article (31) may be presented for reconsideration to the same Board of Directors within six months from the date of rejection.  If the application is rejected for the second time, the applicant may appeal to the appropriate court. 

Article (33)

The industrial free zone certificate shall be revoked if proven that the project owner violated any provisions or if a period of six months has elapsed before initiation of actual work on the licensed project, unless a reasonable excuse for the delay is presented.

Article (34)

The industrial free zone certificate may not be granted except to the persons or the legal entities registered in Palestine whose purpose is to work in the industrial free zone. 

(Back)  (Previous)  (Next)

::::::::::::::::::::::::::::::::::::::::::::::::::::::
 

TOP
 

 

 

© 2004   All Rights Reserved to PIEFZA